SECTION 01320
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. This
Section includes administrative and procedural requirements for documenting the
progress of construction during performance of the Work, including the following:
1. Contractor's
Construction Schedule.
2. Submittals
Schedule.
3. Daily
construction reports.
4. Field
condition reports.
B. See
Division 1 Section "Summary of Multiple
Contracts" for preparing
a combined Contractor's
Construction Schedule.
C. See
Division 1 Section "Payment Procedures" for submitting the Schedule of
Values.
1.2 DEFINITIONS
A. Activity:
A discrete part of a project that can be
identified for planning, scheduling, monitoring, and controlling the construction
project. Activities included in a construction
schedule consume time and resources.
1. Critical
activities are activities on the critical path.
They must start and finish on the
planned early start and finish times.
2. Predecessor
Activity: An activity that precedes another activity in the network.
3. Successor
Activity: An activity that follows another activity in the network.
B. CPM:
Critical path method, which is a method of
planning and scheduling a construction project where activities are arranged based
on activity relationships. Network calculations
determine when activities can be performed and the critical path of Project.
C. Critical
Path: The longest connected chain of interdependent
activities through the network schedule that establishes the minimum overall Project
duration and contains no float.
D. Float:
The measure of leeway in starting and completing an activity.
1. Float
time is not for the exclusive use or benefit of either Owner or Contractor, but
is a jointly owned, expiring Project resource available to both parties as needed
to meet schedule milestones and Contract completion date.
E. Fragnet:
A partial or fragmentary network that breaks
down activities into smaller activities for greater detail.
F. Major
Area: A story of construction, a separate building, or a similar significant construction
element.
1.3 SUBMITTALS
A. Submittals
Schedule: Submit three copies of schedule.
Arrange the following information in a tabular
format:
1. Scheduled
date for first submittal.
2. Specification
Section number and title.
3. Submittal
category (action or informational).
4. Name
of sub-contractor.
5. Description
of the Work covered.
6. Scheduled
date for Architect's final release or approval.
B. Preliminary
Network Diagram: Submit two copies, large
enough to show entire network for entire construction period. Show logic ties for
activities.
C. Contractor's
Construction Schedule: Submit two copies
of initial schedule, large enough to show entire schedule for entire construction
period.
1. Submit
an electronic copy of schedule, using software indicated, on CD-R, and labeled to
comply with requirements for submittals. Include type of schedule (Initial or Updated)
and date on label.
D. CPM
Reports: Concurrent with CPM schedule, submit
two copies of each of the following computer- generated reports. Format for each activity in reports shall contain
activity number, activity description, cost and resource loading, original duration,
remaining duration, early start date, early finish date, late start date, late finish
date, and total float in calendar days.
1. Activity
Report: List of all activities sorted by
activity number and then early starts date, or actual start date if known.
2. Logic
Report: List of preceding and succeeding
activities for all activities, sorted in ascending order by activity number and
then early start date, or actual start date if known.
3. Total
Float Report: List of all activities sorted in ascending order of total float.
E. Daily
Construction Reports: Submit two copies at weekly intervals.
F. Field
Condition Reports: Submit two copies at time of discovery of differing conditions.
G. Monthly
Updated Progress Report: To be updated and submitted monthly including Cash flow
leveling report.
1.4 COORDINATION
A. Coordinate
preparation and processing of schedules and reports with performance of construction
activities and with scheduling and reporting of separate contractors.
B. Coordinate
Contractor's Construction Schedule with the
Schedule of Values,
list of subcontracts, Submittals Schedule, progress reports,
payment requests, and other required schedules and reports.
1. Secure
time commitments for performing critical elements of the Work from parties involved.
2. Coordinate
each construction activity in the network with other activities and schedule them
in proper sequence including the following.
a. Construction
site work activity
b. Long
lead items submittal schedule
c. Long lead items delivery schedule
d. MEP
detailed activity schedule
e. Shop and coordination drawing submission schedule
PART 2 - PRODUCTS
2.1 SUBMITTALS SCHEDULE
A. Preparation:
Submit a schedule of submittals, arranged
in chronological order by dates required by construction schedule. Include
time required for review, re-submittal, ordering, manufacturing, fabrication, and
delivery when establishing dates.
1. Coordinate
Submittals Schedule with list
of subcontracts, the Schedule
of Values, and
Contractor's Construction Schedule.
2. Submit
concurrently with the first complete submittal of Contractor's Construction Schedule.
2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time
Frame: Extend schedule from date established
for the Notice to proceed to date of Substantial
Completion.
1. Contract
completion date shall not be changed by submission of a schedule that shows an early
completion date, unless specifically authorized by Change Order.
B. Activities:
Treat each story or separate area as a separate numbered activity for each principal
element of the Work. Comply with the following:
1. Activity Duration: Define
activities so no activity is longer than 30 days, unless specifically allowed by
Architect.
2. Procurement
Activities: Include procurement process activities
for the following long lead items and major items, requiring a cycle of more than
60 days, as separate activities in schedule. Procurement cycle activities include,
but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal
Review Time: Include review and re-submittal times indicated
in Division 1 Section "Submittal Procedures" in schedule. Coordinate
submittal review times in Contractor's Construction Schedule with Submittals Schedule.
4. Startup
and Testing Time: Include not less than seven days for startup and testing.
5. Substantial Completion: Indicate
completion in advance of date established for Substantial Completion, and allow
time for Architect's administrative procedures necessary for certification of Substantial
Completion.
C. Constraints: Include constraints and work restrictions indicated
in the Contract Documents and as follows in schedule, and show how the sequence
of the Work is affected.
1. Phasing:
Arrange list of activities on schedule by phase.
2. Work
under More Than One Contract: Include a separate activity for each contract.
3. Work
by Owner: Include a separate activity for each portion of the Work performed by
Owner.
4. Work
Restrictions: Show the effect of the following items on the schedule:
a. Coordination
with existing construction.
b. Limitations of continued occupancies.
c. Uninterruptible
services.
d. Partial
occupancy before Substantial Completion.
e.
Use of premises restrictions.
f. Provisions
for future construction.
g. Seasonal variations.
h. Environmental
control.
5. Work
Stages: Indicate important stages of construction for each major portion of the
Work.
6. Other
Constraints: As indicated in the document
D. Milestones: Include milestones indicated in the Contract
Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial
Completion, and Final Completion and as required by the Architect.
E. Contract
Modifications: For each proposed contract
modification and concurrent with its submission, prepare a time-impact analysis
using fragnets to demonstrate the effect of the proposed change on the overall project
schedule.
2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)
A. Preliminary
Network Diagram: Submit diagram within seven
days of date established, commencement form the Notice to Proceed. Outline
significant construction activities for the first 60 days of construction. Include
skeleton
diagram for the remainder
of the Work and
a cash requirement
prediction based on indicated activities.
B. CPM
Schedule: Prepare Contractor's Construction
Schedule using a computerized, cost, resource- loaded, time-scaled CPM network analysis
diagram for the Work.
1. Develop
network diagram in sufficient time to submit CPM schedule so it can be accepted
for use no later than 30 days after date established for the Notice to Proceed.
a. Failure
to include any work item required for performance of this Contract shall not excuse
Contractor from completing all work within applicable completion dates, regardless
of Architect's approval of the schedule.
2. Establish
procedures for monthly monitoring and updating CPM schedule and for reporting progress.
Coordinate procedures with progress meeting and payment request dates.
3. Use
"one workday" as the unit of time. Include list of nonworking days and
holidays incorporated into the schedule.
C. CPM
Schedule Preparation: Prepare a list of all
activities required to complete the Work. Using the preliminary network diagram, prepare
a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated time duration,
sequence requirements, and relationship of each activity in relation to other activities.
Include estimated time frames for the following activities:
a. Preparation
and processing of submittals.
b. Mobilization and demobilization.
c. Purchase
of materials.
d. Delivery.
e. Fabrication.
f. Utility
interruptions
g. Installation.
h. Work
by Owner that may affect or be affected by Contractor's activities.
i. Testing
and commissioning.
2. Critical
Path Activities: Identify critical path activities, including those
for interim completion dates. Scheduled start and completion dates shall be consistent
with Contract milestone dates.
3. Processing:
Process data to produce output data on a
computer-drawn, time-scaled network.
Revise data, reorganize activity
sequences, and reproduce as often as necessary to produce the
CPM schedule within the limitations
of the Contract Time.
4. Format:
Mark the critical path. Locate the critical path near center of network;
locate paths with most float near the edges.
a. Sub-networks
on separate sheets are permissible for activities clearly off the critical path
D. Initial Issue of Schedule: Prepare initial network diagram from a list of
straight "early start-total float" sort.
Identify critical activities.
Prepare tabulated reports showing the following:
1. Contractor
or subcontractor and the Work or activity.
2. Description
of activity.
3. Principal
events of activity.
4. Immediate
preceding and succeeding activities.
5. Early
and late start dates.
6. Early
and late finish dates.
7. Activity
duration in workdays.
8. Total
float or slack time.
9. Average
size of workforce.
E. Schedule
Updating: Concurrent with making at least
monthly revisions to schedule, prepare tabulated reports showing the following:
1. Identification
of activities that have changed.
2. Changes
in early and late start dates.
3. Changes
in early and late finish dates.
4. Changes
in activity durations in workdays.
5. Changes
in the critical path.
6. Changes
in total float or slack time.
7. Changes
in the Contract Time.
2.4 REPORTS
A. Daily
Construction Reports: Prepare a daily construction
report recording the following information concerning events at Project site:
1. List
of subcontractors at Project site.
2. Equipment
at Project site.
3. Material
deliveries.
4. High
and low temperatures and general weather conditions.
5. Accidents.
6. Stoppages,
delays, shortages, and losses.
7. Meter
readings and similar recordings.
8. Orders
and requests of authorities having jurisdiction.
9. Services
connected and disconnected.
10. Equipment
or system tests and startups.
B. Field
Condition Reports: Monthly basis or immediately
on discovery of a difference between field conditions and the Contract Documents,
prepare and submit a detailed report. Submit
with a request for interpretation on approved form by the Architect. Include a detailed description of the differing
conditions, together with recommendations for changing the Contract Documents.
PART 3 - EXECUTION
3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's
Construction Schedule Updating: At monthly
intervals, update schedule to reflect actual construction progress and activities.
Issue schedule one week before
each regularly scheduled progress meeting.
1. Revise
schedule immediately after each meeting or other activity where revisions have been
recognized or made. Issue updated schedule concurrently with the report of each
such meeting.
2. Include
Weekly or Monthly report with updated schedule that indicates every change, including,
but not limited to, changes in logic, durations, actual starts and finishes, and
activity durations.
3. As
the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution:
Distribute copies of approved schedule to
Architect Owner, separate contractors, testing and inspecting agencies, and other
parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary
field offices.
2. When
revisions are made, distribute updated schedules to the same parties and post in
the same locations. Delete parties from
distribution when they have completed their assigned portion of the Work and are
no longer involved in performance of construction activities.
END OF SECTION 01320